PROJECT SHEET

Sheffield Medical Office Building

JAMES E. QUARLES PLANT 1 REPLACEMENT

Project Name: James E. Quarles Plant 1 Replacement

Client: Archer Western

Contract Amount: $1M- $5M

Location: Marietta, Georgia

Duration of Project: Active

Description: As part of a $40 million upgrade, James E. Quarles Water treatment Plant 1 is scheduled to be demolished and replaced. This was the first Cobb County-Marietta water treatment plant and was built in 1952. SSD performed the demolition, minor site excavation and asbestos abatement of the existing Plant 1 filter building, flocculation sedimentation basins and underground clearwells. Over 10,000 yards of concrete was removed and recycled. This scope of work was executed in two phases to maintain daily operations at the facility.